Rock Drilling

Ford Woodhaven

  • Multiple Press Pits Completed with 4 Total Mobilizations

  • 20" Dia. Tie Rod Sleeves Installed with 1" Centerline Tolerance

  • 4'-0" & 4'-6" Caisson Diameters

  • Drill Depth up tp 65' 

  • 8 to 15' Rock Sockets Through 15,000 PSI Limestone Bedrock

  • Engineered Equipment Pick Plan for Each Phase of Work

  • All Work Completed Indoors with Low Overhead Restrictions

  • Worked Double Shifts to Meet Owners Schedule

78 Caissons and 48 Tie Rod Sleeves Completed to Date