Ford Woodhaven
Ford Woodhaven Stamping Plant
78 Caissons and 48 Tie Rod Sleeves Completed to Date
Multiple Press Pits Completed with 4 total mobilizations
20" Dia. Tie Rod sleeves installed with 1" centerline tolerance
4'-0" & 4'-6" caisson diameters
Drill depth up tp 65'
8 to 15' Rock Sockets through 15,000 PSI Limestone bedrock
Engineered Equipment Pick Plan for each phase of work
All work completed indoors with low overhead restrictions
Worked double shifts to meet owners schedule