LG & E Transmission Line Foundations

Drill depth of 60 feet 
 

Over 50 Caisson Foundations Installed

Advanced the shafts with a polymer slurry through wet granular soils.

Limited access and low overhead clearance.

 

 

Four Leg Towers
One ton tower leg stubs embedded directly into the caissons.
Custom fabricated templates used to set and pour all four caissons in one day with precise alignment.
Monopoles
Provided a quality product from start to finish. With over 55 years of experience in this area of foundation work, RSC has perfected the installation procedures for transmission line work. 
Three Leg Towers
Custom fabricated templates used to set and pour all three caissons in one day with precise alignment.